Navi Mumbai’s Rs 236-Crore Science Park Faces Another Delay, Phase 1 Now Due In May 2027

Navi Mumbai’s ambitious Science Park project in Nerul is facing further delays, with the Navi Mumbai Municipal Corporation (NMMC) now targeting May 2027 for the opening of its first phase. The Rs 236-crore development was originally expected to be completed by March 2026.

Spread across 19,999 square metres in Sector 19, the facility is designed to feature a science museum, convention centre, interactive exhibits, educational activities and workshops. Although the main structure has been completed, interior work and exhibit installation remain pending. The second phase, which includes exhibits sourced internationally, does not yet have a confirmed completion date.

City engineer Shirish Aradwad said the civic body plans to open the first phase while work on the remaining facilities continues.

Construction and exhibits follow separate schedules

The project’s structural work was initially scheduled for completion by December 2025, before being pushed to October 2026. The first-phase opening has subsequently been shifted to May 2027. Tenders for interior work have recently been floated, with exhibit installation expected to take another six to seven months.

The project’s estimated expenditure comprises Rs 109 crore for structural construction and Rs 127 crore for interiors and exhibits. Officials have not confirmed whether the delays will affect the overall budget.

The proposed facility will feature 225 exhibits covering areas such as biology, environmental science, energy engineering and space science. Its displays are expected to include scientific models, three-dimensional presentations, audio-visual films and educational material.

Imported exhibits add to uncertainty

For the second phase, NMMC plans to visit international science facilities to identify exhibits that meet global standards. However, procurement, transportation and installation timelines remain unclear, leaving the completion schedule uncertain.

Municipal commissioner Kailas Shinde has emphasised the importance of accessible scientific literature, quality displays and internationally benchmarked exhibits. The corporation has also consulted Indian and overseas scientists during the planning process.

Delivery beyond construction

The phased opening could allow residents and tourists to access part of the facility before the entire project is ready. However, the number of exhibits available initially and the sections scheduled to open have not been specified.

The project’s long-term success will depend on more than completing the building. Timely exhibit installation, maintenance, updated scientific content and sustained educational programmes will be essential to establish the Science Park as a useful public institution.