The Thane Municipal Corporation (TMC) has revived its proposal to prepare an integrated development plan for the area surrounding the upcoming Thane High-Speed Railway station, part of the Mumbai-Ahmedabad Bullet Train project. The proposed plan will cover approximately 478 hectares spread across the jurisdictions of Thane and Kalyan-Dombivli municipal corporations.
Of the total area, nearly 218 hectares fall within TMC limits, while the remaining 260 hectares come under the Kalyan-Dombivli Municipal Corporation (KDMC).
The Mumbai-Ahmedabad High-Speed Rail Corridor is being developed jointly by the Central Government and the Japan International Cooperation Agency (JICA). While the National High-Speed Rail Corporation Limited (NHSRCL) is overseeing the construction of the railway station, the surrounding area will be developed by the respective local planning authorities.
A separate development plan is proposed for the station precinct at Mhatardi. Within Thane, the planning area will include portions of Mhatardi, Dativali, Betawade and Agasan villages. On the KDMC side, parts of Ayre, Kopar, Bhopar, Nandivli, Panchanand, Katai and Usarghar villages are expected to be covered.
The proposed framework aims to bring multiple transport facilities together, including a circular Metro connection to the Bullet Train station, the proposed Metro Line 14 and a water transport jetty along the Ulhas River. The broader planning area will encompass portions of nearly 10 villages across both civic jurisdictions.
The initiative follows directions from the state government. KDMC has conveyed its consent to the proposal, while the Mumbai Metropolitan Region Development Authority (MMRDA) has also stated that it has no objection to the planning exercise.
Earlier Planning Exercise Faced Delays
The intention to prepare a development plan for the station precinct was first published in the Government Gazette on October 28, 2025, following an amendment to the Maharashtra Regional and Town Planning Act on August 29, 2025. The amendment introduced a special provision for preparing Local Area Plans.
However, the stipulated six-month deadline for publishing the draft plan passed without its completion. Uncertainty surrounding key transport links, particularly the circular Metro route, Metro Line 14 and water connectivity along the Ulhas River, contributed to the delay.
The TMC administration has now proposed restarting the exercise with these connectivity requirements taken into account. The proposal has been placed before the corporation’s General Body for approval.
Following approval, the state government will issue a notification inviting objections and suggestions from residents and other stakeholders. The subsequent planning process will take into consideration the feedback received from the public.