The Maharashtra Coastal Zone Management Authority (MCZMA) has granted coastal clearances to three infrastructure projects in Mumbai, covering a new power transmission network, a proposed marina at Cuffe Parade and the shifting of electricity transmission lines to facilitate a flyover at Mankhurd.
The approvals are expected to strengthen the city’s electricity infrastructure, develop waterfront facilities and improve road connectivity between Mumbai’s eastern suburbs and Navi Mumbai. However, the projects will also involve construction in environmentally sensitive coastal zones.
Cuffe Parade Marina Project
The proposed marina near Cuffe Parade received approval at an MCZMA meeting held on November 2. Its promoter, Rashmi Developments Pvt Ltd, had secured a no-objection certificate from the Mumbai Metropolitan Region Development Authority (MMRDA), subject to ensuring that the development does not conflict with the proposed Nariman Point-Cuffe Parade coastal bridge.
The project will include an inland water transport terminal, promenade, immigration centre, jetty, yacht ramp, breakwater and navigational channel. It will also feature an anchored cruise vessel functioning as a floating hotel. Managing director Raj Pradhan said construction is expected to begin in January 2027.
Vikhroli-Dharavi Electricity Corridor
Tata Power’s proposed 400 kV Vikhroli-Dharavi transmission link will form the first phase of a larger electricity ring network planned for Mumbai. The infrastructure is intended to meet increasing power requirements arising from metro projects, redevelopment activities and data centres.
The development includes an overhead transmission line, a gas-insulated substation at Vikhroli and an underground cable connecting Dharavi. The proposed Dharavi substation will have a capacity of 1,000 MVA.
However, the project will affect 1.87 hectares of mangrove forest. A forest department assessment found that 598 mangroves and 60 other trees would be impacted, with 452 trees proposed for removal. Tata Power is exploring land in Palghar for compensatory plantation.
Mankhurd Flyover Connectivity
The authority has also approved shifting five transmission lines obstructing road expansion work near Mankhurd. The relocation will facilitate a flyover at the Ghatkopar-Mankhurd Link Road junction, where commuters reportedly face delays of up to 45 minutes during peak hours.
The relocated towers will occupy 29,533.93 square metres within the coastal regulation zone of the Thane Creek Wildlife Sanctuary’s eco-sensitive area.
Source: Hindustan Times