Several sections of the Brihanmumbai Electric Supply and Transport (BEST) undertaking’s underground electricity network require urgent replacement, with some cables having been in service for 70 to 80 years. However, a proposed Rs 200-crore project to lay new cables and strengthen the infrastructure remains delayed due to pending road excavation permissions from the Brihanmumbai Municipal Corporation (BMC).
According to a BEST official, only around one kilometre of work has been completed so far, as clearances for digging roads have held up the remaining activities. Officials are concerned that large-scale execution may not begin before January. “If permissions are in place, we can expedite the project and ensure reliable and uninterrupted supply with minimum or zero faults,” the official added.
BMC Additional Municipal Commissioner Abhijit Bangar said the civic body is currently in its working season and will issue the required permissions. “During monsoon, we restrict permission for digging roads. As for BEST, they have escalated the issue at our level and requested for permissions. The process had been initiated,” he added.
Bangar also pointed to technical difficulties with the newly introduced online trenching permission system. “There was some server issue, which is being resolved. From Monday, permissions will be cleared and will be real time,” he said.
The delay has added to concerns over the condition of BEST’s electricity distribution network. Officials said recurring cable failures and temporary restoration measures are increasing pressure on operational lines. In certain areas, damaged cables are being patched with insulating tape, while electricity supply is diverted through alternative cables until permanent repairs can be undertaken.
Nearly 2,500 cable faults recorded over the past few years are still awaiting permanent rectification. Consumer complaints related to power disruptions have also increased from approximately 6,500 in 2024-25 to nearly 7,500 in 2025-26.
Meanwhile, BEST is planning to recruit more than 2,000 employees for its electricity division to improve cable installation, replacement and maintenance work.