Mumbai-Ahmedabad Bullet Train Project Records Key Construction Milestones

August 20, 2025: The Mumbai-Ahmedabad High Speed Rail (MAHSR) project, India’s first bullet train corridor, has reached several important milestones as construction accelerates across Gujarat and Maharashtra. Officials confirmed that foundation work has been completed on 406 kilometres of the 508-kilometre corridor, with track laying already underway on a 127-kilometre viaduct. Progress on supporting structures […]
Is India’s First Bullet Train Building More Than Connectivity?

August 8, 2025: India’s first bullet train project—the Mumbai–Ahmedabad High-Speed Rail (MAHSR)—promises more than just a revolution in travel. At 508 kilometres in length and with a journey time of just over two hours between two of the country’s key economic centres, the MAHSR is already influencing property markets along its route. From Tier-2 cities […]
Mumbai- Ahmedabad Bullet Train To Launch In 2029

August 1, 2025: The Ministry of Railways is making swift progress on India’s first bullet train project — the Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor — spanning 508 kilometres. The project is being executed by the National High Speed Rail Corporation Limited (NHSRCL). With a total estimated cost of Rs 1.08 trillion, approximately Rs 7,880 crore […]
Mumbai-Ahmedabad Bullet Train: 8 Stations To Be Ready By 2027, Says Railways

July 30, 2025: The National High Speed Rail Corporation Limited (NHSRCL) is set to complete the construction of eight stations on the Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor in Gujarat by December 2027. The 508-km corridor, India’s first bullet train project, aims to revolutionize intercity travel and place India among global leaders in high-speed rail infrastructure. […]
India’s First Bullet Train Targets Its Launch In 2029

July 28, 2025: The Mumbai-Ahmedabad bullet train, India’s ambitious high-speed rail initiative, is now slated for completion by December 2029. This flagship project aims to significantly reduce travel time between the two major cities to approximately two to three hours, offering a faster, more efficient alternative to current transport options. In a written submission to […]
Mumbai-Ahmedabad Bullet Train: 16 Of 21 River Bridges Completed In Gujarat

July 11, 2025: The National High-Speed Rail Corporation Limited (NHSRCL) has announced a significant milestone in the construction of the Mumbai-Ahmedabad high-speed rail corridor, with 16 out of 21 river bridges now completed in Gujarat. This development marks steady progress along the 352-kilometre stretch within the state, forming a crucial part of India’s first bullet […]
Mumbai-Ahmedabad Bullet Train Tunnel Project Hits Major Delay

June 24, 2025: India’s flagship high-speed rail initiative—the Mumbai–Ahmedabad bullet train corridor—has hit a significant roadblock, with three vital Tunnel Boring Machines (TBMs) stranded at a Chinese port. The delay, attributed to a lack of clearance from Chinese authorities, jeopardises the timeline for the critical underground stretch between Mumbai’s Bandra Kurla Complex (BKC) and Shilphata […]
Mumbai-Ahmedabad Bullet Train Project Advances Rapidly

India’s ambitious high-speed rail project, the Mumbai-Ahmedabad bullet train corridor, is set to revolutionise inter-city travel across Maharashtra, Gujarat, and Dadra and Nagar Haveli. Spanning 508 kilometres, the route will feature 12 strategically placed stations, including Mumbai’s Bandra Kurla Complex, Thane, Surat, Vadodara, Ahmedabad, and Sabarmati, among others. While Shinkansen train trials are underway in […]
Bullet Train Progress: Mumbai-Ahmedabad Route Hits 60% Milestone with 300 Km Viaduct Ready

India’s first high-speed rail corridor between Mumbai and Ahmedabad has reached a significant construction milestone with the completion of 300 km of viaducts, out of a total alignment of approximately 508 km. The achievement was marked by the launch of a 40-metre-long full-span box girder near Surat, Gujarat. According to the National High Speed Rail […]
300 Km Viaduct Construction Completed For Mumbai-Ahmedabad Bullet Train

The Mumbai-Ahmedabad high-speed rail project has reached a significant construction milestone, with 300 km of viaducts now completed, according to the National High Speed Rail Corporation Limited (NHSRCL). The landmark was achieved following the launch of a 40-metre-long girder near Surat in Gujarat. Of the 300 km of superstructure, 257.4 km was built using the […]