Mumbai Trans Harbour Link: 93 Per Cent Work Complete, On Track To Open In December 2023

The under-construction Mumbai Trans Harbour Link (MTHL) crossed another milestone on Saturday when the segment casting work for Package-2 of the project was completed. “It is a wonderful achievement as we cross one more milestone and move a little closer towards project completion. This engineering marvel – MTHL – is now 93 per cent complete,” said S V R Srinivas

A total of 3,132 segments have been casted for Package-2 of the project. The MTHL bridge has been split into four packages – while packages 1 and 2 are sea based, package 3 is on land. Package-1 spans from Sewri (0.00 km) to 10.380 km and Package-2 is from Sewri (10.380 km) to 18.189 km. Package-3 covers the stretch of the bridge from Sewri (18.187 km) and continues for 3.60 km, concluding on land at 21.80 km

https://swarajyamag.com/news-headlines/mumbai-trans-harbour-link-93-per-cent-work-complete-on-track-to-open-in-december-2023

Source:

Leave a Reply

Your email address will not be published. Required fields are marked *