The Mumbai Metropolitan Regional Development Authority (MMRDA) has said that it has erected 3,603 out of 4,929 pillars or 73 per cent of the work on the upcoming 6 new Mumbai Metro lines in the Mumbai Metropolitan Region (MMR), here on Thursday. These include the Metro 2B (D.N. Nagar-Mandale) 614 out of 1,109 pillars or 50.70 per cent
Metro 4 and 4A (Wadala-Kasarvadavali) 973 out of 1,476 and 143 out of 221 respectively, or 55 per cent completion.Metro 5 Phase I (Thane-Bhiwandi) 440 out of 464 pillars or 78.40 per cent done; Metro 6 (Swami Samarth Nagar-Vikhroli) 657 out of 768 or 70.75 per cent completed; and Metro 9 (Dahisar-Mira Bhayander) 776 out of 900 or 61.28 per cent done. This was despite the major challenges of construction activities in a congested city with heavy traffic and care was taken to do most activities during the night time