Mumbai Metropolitan Region Development Authority (MMRDA) has achieved more than 96% progress on the Mumbai Trans Harbour Link Road (MTHL) as work is in full swing to complete it by this December. All works related to building the viaduct and barriers are done and now the focus is on asphalting, installation of light poles, CCTV cameras and toll infrastructure.
An MMRDA official said, “All the ramps at Sewri Interchanges (Sewri, Shivajinagar and Chirle) connecting local roads on either side are complete. Bituminous works on these roads are in progress.” The bidding process for appointment of a contractor for a connector between Chirle and the Expressway is in process. A total of 1,212 lighting poles are to be installed as part of the project, of which 629 poles are already in place.