There will be traffic bottlenecks on the Western Express Highway in Kandivali, Mumbai, at least till August

A Medium article claims that because to the gas pipeline near the piling site, the expansion construction on the Akurli Underpass in Kandivali East, which had begun in 2019, was halted in June 2023.

In contrast to the initial 40-day deadline, Mahanagar Gas Limited (MGL) took six months, according to Mumbai Metropolitan Regional Development Authority (MMRDA) authorities, to relocate the gas pipeline. Since last year, there have been significant traffic backups on Western Express Highway (WEH) affecting northbound traffic because the underpass enlargement project is still unfinished.

Source – Microsoft Start News