Rs 10,986-Crore Metro Line 2B Stuck Over Land Dispute With 55-Year-Old Resident

The dispute dates back to changes in the Metro's alignment approved in 2015

A prolonged housing dispute involving a 55-year-old Mumbai resident is delaying the completion of a crucial section of the Rs 10,986-crore Metro Line 2B project. Authorities are unable to complete a 185-metre stretch near Juhu Circle until the resident vacates the building where he has lived since childhood, according to a report by a news organisation.

The 23.643-km elevated Metro corridor connects several suburban locations across Mumbai. However, on the upcoming eight-kilometre Andheri-Khar stretch, track installation remains incomplete over a small section passing above Juhu Gulmohar Cooperative Housing Society. The society comprises two ageing residential buildings constructed in 1980, most of whose occupants have already moved out.

The dispute has continued for more than eight years, involving legal proceedings in the Bombay High Court, unsuccessful negotiations and a proposed land exchange involving a nearby public garden.

The incomplete section has prevented the Mumbai Metropolitan Region Development Authority (MMRDA) from finishing track installation, setting up overhead electrical equipment, energising the corridor and commencing trial runs. Officials estimate that the stretch has already faced a delay of at least eight months.

The issue originated in 2015 when changes to the Metro alignment affected the housing society’s redevelopment plans. Since airport-related height restrictions limited the possibility of modifying the route, authorities explored an alternative arrangement.

Under the proposed solution, MHADA offered the society an alternative 2,345-square-metre plot at nearby Tilak Udyan, allowing the existing property to be cleared for Metro construction.

The arrangement gained momentum in 2025 after MMRDA agreed to contribute Rs 34 crore towards facilitating the land exchange. By September 2026, the lease transfer and changes in land use had reportedly been completed.

However, the project continues to face one final obstacle. The housing society and its developer are yet to execute a permanent alternate accommodation agreement. This agreement is necessary to activate relocation benefits and facilitate the remaining resident’s departure.

Until the agreement is signed and the buildings are vacated and demolished, construction of the missing 185-metre Metro section cannot proceed, further delaying a key connectivity project for Mumbai.

Source: Money Control