The Brihanmumbai Municipal Corporation (BMC) has proposed a Rs 9.08-crore flood mitigation project to strengthen and widen a 420-metre section of the Poisar River in Kandivali East. The initiative aims to reduce recurring waterlogging in Hanuman Nagar, a low-lying neighbourhood that has experienced flooding during intense monsoon showers in recent years.
The project, being executed through the BMC’s R/South ward, will cover the river stretch between Kurar Culvert and the Western Railway area. As part of the plan, the civic body intends to construct a reinforced cement concrete (RCC) retaining wall to prevent overflowing river water from entering nearby residential settlements.
Preparatory work has begun, with the ward office removing encroachments along the identified stretch. Some hutment residents affected by the project have been offered alternative accommodation, while the remaining structures are expected to be cleared before construction begins.
The proposed wall is expected to keep the river within its designated channel during heavy rainfall, reducing the possibility of flooding in surrounding residential areas.
The BMC received five bids against its initial estimated cost of Rs 8.16 crore. Following technical scrutiny, all five contractors were found eligible. Pralita Infraprojects emerged as the lowest bidder, quoting Rs 5.77 crore, which is 29.29% below the estimated amount, excluding GST and other charges. After reviewing its rate analysis, the administration recommended accepting the offer.
The overall project expenditure, including taxes, contingencies, utility shifting, supervision and other provisions, has been calculated at ₹9.08 crore.
The contractor will have 12 months to complete the work, excluding the monsoon period. It will also be responsible for removing accumulated silt and obstructions to ensure uninterrupted stormwater movement throughout the contract period.
Funding has been provisionally allocated in the BMC’s 2026-27 capital budget, with additional requirements to be considered in subsequent budgets.
The proposal was placed before the Standing Committee on Friday but was not discussed. It is expected to be taken up next week, along with consideration by the Construction Committee (suburbs).