NGT Imposes 5% Environmental Penalty On Pali Hill’s Sandhu Palace For Construction Without Clearance

The National Green Tribunal (NGT) has directed Sandhu Builders to pay environmental compensation amounting to 5% of the total project cost for developing the 18-storey Sandhu Palace in Mumbai’s Pali Hill without obtaining mandatory environmental clearance (EC).

The tribunal has also instructed the Brihanmumbai Municipal Corporation (BMC) to stop issuing further occupation certificates for the building. Additionally, the developer has been prohibited from creating any new third-party interests in the property until the required clearance is secured.

A bench comprising judicial member Justice Dinesh Kumar Singh and expert member Dr Sujit Kumar Bajpayee directed the Maharashtra State Environment Impact Assessment Authority (SEIAA) to assess the environmental damage and determine suitable restoration measures. The developer will have to bear these costs separately. SEIAA has also been asked to decide the pending EC application within three months.

Sandhu Builders must deposit the 5% compensation with the Maharashtra Pollution Control Board (MPCB) within two months. The amount will be utilised for environmental improvement in the surrounding area.

Tribunal Rejects Developer’s Defence

The directions followed two applications filed by Chetak Cooperative Housing Society Ltd and Pratap Lal Teli, represented by advocate Aditya Pratap. They challenged the legality of the project, which has a total built-up area of 40,317.33 square metres.

The developer argued that its building plans were approved in February 2006, before the Environmental Impact Assessment notification introduced in September that year. It also cited a 2017 communication from the environment ministry stating that separate clearance was not required for certain construction projects below 1.5 lakh square metres.

However, the tribunal rejected this defence, noting that relevant provisions of the 2016 notification had been quashed in an earlier NGT judgment. It held that environmental clearance was necessary from October 2008, when the first expansion took place.

No Demolition Order at Present

The bench declined to direct demolition, noting that a partial occupation certificate had already been issued and third-party interests had been created. It observed that “demolition cannot be ordered unless those affected are impleaded as respondents”.

The tribunal also described SEIAA’s prolonged failure to decide the application as “strange” and indicated that disciplinary proceedings could be initiated against officials responsible for the delay.

Source: Hindustan Times