The long-awaited Mumbai-Goa highway project continues to face delays, with approximately eight kilometres of roadwork remaining incomplete across five stretches in Maharashtra. The project has also witnessed a substantial increase in costs, with estimates indicating an escalation of more than Rs 2,000 crore in the final stages, according to an investigation by The Indian Express.
The 592-km National Highway 66 (NH-66) project was initially conceived in 2006 as part of a four-lane road corridor connecting Panvel near Mumbai to Kanyakumari. Construction began in October 2007, with the first 21-km section near the Goa border completed in 2013. Most other sections received approval in 2015-16, while construction contracts were awarded during 2017-18.
The highway was initially scheduled for completion by December 2018, as informed to Parliament in December 2016. The deadline was subsequently extended to 2021, but several sections continued to encounter obstacles, including contractor-related issues and land acquisition delays.
The five pending stretches include two bypasses covering approximately three kilometres, a 192-metre bridge, a 1.8-km flyover, hill-cutting work across four locations spanning 1.5 km, and other ongoing construction activities. Progress across these packages ranges between 89% and 98.5%.
Union Road Transport and Highways Ministry Secretary V Umashankar said, “In the last two years, a lot of work was done on stalled stretches and 99% of the highway is through now. All pending work will be completed by April next year.”
The Maharashtra section’s estimated project cost has increased by nearly 44%, rising from Rs 12,532 crore to over Rs 18,100 crore. Officials attributed the escalation to land acquisition, changes in project scope, site-related constraints and additional underpasses demanded by residents.
The delays have also been linked to financial difficulties, loan defaults, land acquisition complications and local protests. Some contractors have faced termination, while pending work has been reassigned to other agencies.
With the Goa section already completed, the remaining Maharashtra stretches are crucial to establishing uninterrupted connectivity between Mumbai and Goa. The Centre is now targeting April 2027 for completing the highway.
Source: The Indian Express