BMC To Pay Rs 3.17 Crore Metro Cess To Secure United Mills Land For Textile Museum

Textile Museum being constructed inside India United Mills number 2 and 3 at Byculla, in Mumbai

The Brihanmumbai Municipal Corporation (BMC) has proposed spending Rs 3.17 crore towards Metro cess to facilitate the transfer of 34,584.34 square metres of land at the defunct India United Mills No. 2 and 3 in Mazagaon to the civic body. The property is earmarked for developing a recreation ground and a textile museum.

The proposal has received administrative clearance and will be presented before the BMC Standing Committee on Wednesday. The payment will be made to the Collector of Stamps, Mumbai City, to register the land transfer agreement between the National Textile Corporation (NTC) and the municipal corporation.

The transfer process has remained stalled since April 2024, when the stamp authorities sought Rs 16.12 crore as stamp duty from NTC. The corporation challenged the demand, preventing registration of the transfer document.

The BMC subsequently sought relief under a Maharashtra government order dated October 31, 2003, which provides stamp duty concessions for certain land transfers made free of cost to local authorities in return for transferable development rights (TDR) or floor space index (FSI) for public amenities.

However, the Collector of Stamps maintained that approval from the state’s Urban Development Department was necessary to waive the 1 per cent Metro cess. Municipal Commissioner wrote to the department on January 13, 2026, requesting an exemption, but the government has not yet issued its decision.

To avoid further delays, the BMC has decided to make the payment from its own funds, with the possibility of receiving a refund if the exemption is subsequently granted.

The larger property measures 64,947.34 square metres. NTC had handed over advance possession of 61,056.89 square metres to the BMC on January 7, 2009, for recreational development. A state notification issued on December 29, 2016, subsequently earmarked 44,000 square metres for a recreation ground and textile museum.

According to NTC’s September 6, 2024 communication, museum construction is progressing in phases across approximately 34,584.34 square metres. The BMC has appointed JSW through the CSA mechanism to execute the project, without bearing its construction expenses.

The cess has been calculated using the 2026-27 ready reckoner rate of Rs 68,140 per square metre and an FSI of 1.33. The payment is expected to facilitate the land transfer and enable the public amenities envisaged under Development Plan 2034.