The Mumbai Railway Vikas Corporation (MRVC) has introduced an advanced soil strengthening technique to accelerate construction of the fifth and sixth railway lines between Borivali and Virar. The technology, called Prefabricated Vertical Drain (PVD), is being implemented along the Dahisar-Mira Road section to improve ground conditions before railway embankment construction.
The method is expected to bring down the time required for soil consolidation from several years to approximately six months, depending on ground conditions. It addresses a major engineering challenge along the corridor, where soft soil requires strengthening before supporting heavy railway infrastructure.
Under the PVD technique, specially designed vertical drains are inserted into the soil to create channels through which trapped water can escape. This speeds up the natural settlement process and increases the ground’s strength. MRVC estimates that the method can achieve nearly 90 per cent soil consolidation within six months under favourable conditions, reducing the risk of uneven settlement and improving embankment stability.
The corporation has planned to install approximately 3.20 lakh running metres of vertical drains between Dahisar and Mira Road. One specialised installation machine has already been deployed, with the capacity to lay around 3,000 running metres daily. Nearly 30,000 running metres of drains have been completed so far. Additional machinery will be introduced depending on construction-site availability and project requirements.
The Borivali-Virar fifth and sixth line expansion is a significant capacity enhancement initiative for Western Railway. Currently, suburban and long-distance trains share tracks along several sections, restricting operational flexibility and affecting service movement. The additional lines are expected to separate these operations, minimise conflicts and create scope for improving suburban train services.
Commenting on the initiative, Sunil G Udasi, Chief Manager (Corporate Coordination), MRVC, said the corporation was adopting modern construction technologies and engineering practices to speed up project execution while maintaining safety, quality and long-term infrastructure stability.
The adoption of PVD technology is expected to help overcome ground-related construction challenges and improve the pace of this important suburban railway expansion.