Mumbai’s east-west road connectivity is set to receive a major boost as construction of the double-decker Elphinstone Road bridge advances under the Sewri-Worli Connector project. The Mumbai Metropolitan Region Development Authority (MMRDA) has reported that work on the main railway overbridge (ROB) has reached 63% completion, marking significant progress on the infrastructure project.
According to the authority’s latest update shared on November 23, construction of the approach sections at both the Sewri and Worli ends is also progressing. The bridge is being developed with two levels to accommodate local commuters as well as motorists travelling longer distances across the Mumbai Metropolitan Region.
“The new bridge will strengthen east-west connectivity and provide a link between Atal Setu and the Coastal Road,” MMRDA stated.
Two decks to serve different traffic requirements
The reconstructed Elphinstone Road bridge will feature separate levels for local and regional traffic. The lower deck will be dedicated to vehicles travelling within the surrounding neighbourhoods, while the upper deck will accommodate traffic using the Sewri-Worli Connector.
This arrangement is expected to separate local vehicular movement from longer-distance journeys, allowing both categories of commuters to use the same infrastructure more efficiently.
Improved connectivity across Mumbai
The bridge is an important component of the Sewri-Worli Connector, which will establish a direct road connection between Atal Setu, the Bandra-Worli Sea Link and the Mumbai Coastal Road. The improved route is expected to benefit motorists travelling between Navi Mumbai, Central Mumbai, South Mumbai and the western suburbs.
Sewri-Worli Connector construction update
The main railway overbridge has crossed the 60% construction mark, while excavation, structural work and steel reinforcement activities continue at the site. Approach road construction is also underway on both sides of the bridge.
The Sewri-Worli Connector is a 4.5-km, four-lane elevated corridor. MMRDA anticipates that the project could increase vehicular traffic on Atal Setu by approximately 15-20%.
However, the authority has not announced a revised completion schedule or an expected opening date for the double-decker bridge.
Source: Financial Express