Mumbai CSMT Redevelopment Deadline Extended To December 2028, Only 30% Work Completed

deadline for redevelopment of the Chhatrapati Shivaji Maharaj Terminus (CSMT) has been pushed back by nearly 2.5 years

The redevelopment of Mumbai’s Chhatrapati Shivaji Maharaj Terminus (CSMT), a UNESCO World Heritage Site, is now expected to be completed by December 2028, nearly two-and-a-half years later than the original mid-2026 deadline. The extension has been necessitated by the need to minimise disruptions to suburban and long-distance train services and incorporate additional work, including roofing over platforms.

An official from the Rail Land Development Authority (RLDA), which is overseeing the project, said: “The complexity of undertaking redevelopment at an operational railway station is immense,” said an official from the Rail Land Development Authority (RLDA), which is executing the project. “More so at CSMT, which has 18 platforms, daily footfall of over 600,000 and limited working space.”

Currently, around 30% of the overall work has been completed. Construction of the proposed elevated concourse linking all 18 platforms, one of the project’s major components, is yet to begin.

However, Madhu Kotian, president of Mumbai Rail Pravasi Sangh, questioned the delay, saying it was causing inconvenience to commuters. “Either the contractor is not being paid on time or there is a severe problem with availability of manpower,” Kotian said.

The redevelopment aims to turn CSMT into an airport-like integrated transport hub, with improved passenger facilities, better movement across platforms and conservation of its heritage architecture. The project covers approximately 450,000 square metres, including 200,000 square metres of fresh construction and 250,000 square metres of upgraded infrastructure.

Launched in January 2023, the work initially focused on refurbishing platforms used by long-distance trains. Following the completion of platforms 16 and 17, platforms 14 and 15 were shut on October 1 for 75 days. However, the reopening date has now been extended from December 15 to January 31, 2027, to accommodate additional roofing work.

The construction challenges have also affected train operations, with certain services being diverted to other platforms or short-terminated at Dadar and Thane.

The elevated concourse will be developed alongside platform upgrades, providing improved passenger circulation and space for restaurants, hotels and other facilities. Work will subsequently move to platforms 10–13.

The project also involves two new station buildings along P D’Mello Road, featuring railway offices and commercial facilities. Their foundation work is underway.

An RLDA official said the project requires nearly 40,000 metric tonnes of structural steel, with fabrication workshops and specialised cranes deployed to manage the extensive construction.

The original project cost of Rs 2,450 crore has also been revised to Rs 3,155.50 crore, with approval from the Railway Ministry awaited.

RLDA officials maintained that major railway station redevelopment projects generally require four to six years. They added: “The overall project timeline has been revised only once. Dates assigned to individual components and phased commissioning should not be treated as repeated extensions of the entire project,” an RLDA official said.

Source: Hindustan Times