Mumbai’s Four New Railway Bridges Set To Ease Traffic Bottlenecks

Mumbai is set to get four major road overbridges over the next two years, aimed at easing congestion at some of the city’s busiest railway crossings. The projects, collectively estimated at Rs 1,179 crore, are being developed jointly by the Brihanmumbai Municipal Corporation (BMC) and Maharashtra Rail Infrastructure Development Corporation (MRIDC). Three of the upcoming […]

BMC Set To Begin Tunnelling For Goregaon-Mulund Link Road, Key Phase Likely To Start This Weekend

The Brihanmumbai Municipal Corporation (BMC) is expected to begin tunnel excavation for the Goregaon-Mulund Link Road (GMLR) project this weekend, marking a significant milestone in one of Mumbai’s largest road infrastructure projects. The civic body has completed the assembly of the first Tunnel Boring Machine (TBM) and is awaiting approval from Chief Minister Devendra Fadnavis […]

Worli–Sewri Elevated Connector Nears Milestone, 62% Work Completed; September 2026 Target Set

December 17, 2025: The Worli–Sewri Elevated Connector, a key transport infrastructure project aimed at easing Mumbai’s east–west traffic movement, is progressing steadily and is expected to be completed by September 2026. Maharashtra Industries Minister Uday Samant informed the state legislative assembly that nearly 62% of the project work has already been completed. Given its strategic […]

Mahalaxmi Cable-Stayed Bridge Takes Shape: 45% Work Done, Opening Targeted Next Year

December 13, 2025: One of Mumbai’s key urban infrastructure projects, the Mahalaxmi cable-stayed bridge, is steadily progressing and is expected to become operational next year. Designed to significantly ease congestion in South Mumbai, the four-lane east–west connector has completed nearly 45 per cent of its construction, according to the Brihanmumbai Municipal Corporation (BMC). The proposed […]

Work On Mumbai’s Orange Gate–Marine Drive Underground Tunnel Reaches 14% Completion

December 3, 2025: Around 14% of construction on the underground tunnel connecting Orange Gate on the Eastern Freeway to Marine Drive has been completed, the Mumbai Metropolitan Region Development Authority (MMRDA) announced on Tuesday. The Rs 8,056-crore project, designed to significantly improve east–west connectivity in the city, is slated for completion in 54 months. Once […]

First Phase Of 12-km Goregaon–Mulund Link Road Set For 2026 Opening

December 1, 2025: The first phase of the 12.2-km Goregaon–Mulund Link Road (GMLR), a major cross-city connector being built by the Brihanmumbai Municipal Corporation (BMC), is expected to be operational by 2026. The corridor will eventually link Goregaon in the western suburbs to Mulund in the eastern suburbs through a combination of tunnels, bridges, and […]

Mumbai Set For Major Connectivity Transformation As CM Fadnavis Accelerates Key Infrastructure Projects

November 27, 2025: Maharashtra Chief Minister Devendra Fadnavis has outlined an ambitious vision to significantly improve Mumbai’s connectivity, announcing that crucial infrastructure projects across the city will be completed by 2032. He emphasised that ongoing and upcoming works are being fast-tracked to reduce congestion and provide alternative routes for smoother travel. According to the Chief […]

MMRDA Installs Key 52 Metre Steel Span On Andheri-JVLR Missing Link, Marking Major Breakthrough

November 19, 2025: The Mumbai Metropolitan Region Development Authority (MMRDA) has completed a significant construction milestone on the Andheri–JVLR Missing Link project with the installation of a 52-metre steel span at the high-traffic Infinity Mall junction in Andheri West. Executed within an extremely constrained transit zone between Metro Lines 2A and 6, the launch represents […]

BMC’s Mahalaxmi Cable-Stayed Bridge 45% Complete; Project Now Set For December 2026

November 04, 2025: Work on the Brihanmumbai Municipal Corporation’s (BMC) first-ever cable-stayed bridge over the Mahalaxmi railway tracks has reached 45 per cent completion, civic officials confirmed. Originally slated for completion in March 2024, the project has been delayed due to encroachments, utility relocations, and tree transplantation, with the new deadline now extended to December […]