Thousands of commuters travelling through Parel and Prabhadevi railway stations are facing longer walking routes and increased congestion after Central Railway (CR) closed a staircase connecting the eastern side of Parel station to the adjoining road. The closure, implemented around 7-10 days ago, is part of preparations for the proposed fifth and sixth railway lines between Kurla and Parel.
The affected staircase belongs to a six-metre-wide foot overbridge (FOB) constructed in 2023 to manage increasing passenger movement between the two stations. Its temporary closure has diverted pedestrians towards an older and narrower bridge associated with the September 29, 2017, Elphinstone Road stampede, which claimed 23 lives and injured 39 people.
Railway workers have started removing flooring and dismantling sections of the staircase. CR plans to extend the bridge towards the eastern side, with supporting pillars already installed. The additional railway tracks will pass beneath the extended structure.
“We will be extending the FOB further towards the east, for which pillars have already been installed. Below this extended FOB, the two new rail lines will be laid. We expect this work on the FOB to continue until October 2027,” a CR official said.
The Parel-Prabhadevi station complex handles approximately 3-4 lakh passengers every day. While access from the western side remains unaffected, commuters entering and exiting through the eastern side must use alternative routes.
The fifth and sixth lines between Kurla, Parel and CSMT form part of a railway expansion project originally sanctioned in 2008 to reduce pressure on Mumbai’s suburban network.
The construction may also affect station facilities recently upgraded at Parel under the Amrit Bharat Station Scheme at a cost of Rs 19 crore. Ticket counters, staff offices, the station master’s cabin and elevated two-wheeler parking may require relocation.
“The offices and ticket counter need to be moved to ensure space for the new rail lines. Yet we are trying to squeeze in as much as possible to utilise the space and reduce shifting,” another CR official said.
The project has also faced delays due to land acquisition and rehabilitation issues, including the resettlement of 714 project-affected persons, reportedly cleared earlier this year.
The proposed Rs 500-crore Parel terminus will be developed on the site of the century-old railway workshop.