Mumbai’s Deonar Waste-to-Energy Project Set For December Trials, Operations Expected In 2027

Mumbai’s first large-scale waste-to-energy facility at the Deonar dumping ground is nearing completion, with the Brihanmumbai Municipal Corporation (BMC) planning to commence trial operations in December 2026. The Rs 648-crore project is approximately 93% complete and is expected to become operational by early 2027.

Initially scheduled for completion in October 2025, the project faced setbacks due to logistical challenges, an increase in planned power generation capacity and delays in obtaining statutory approvals.

The facility is designed to process 600 tonnes of fresh municipal solid waste every day and generate up to 8 megawatts (MW) of electricity. The BMC will conduct trials over one to two months to evaluate the plant’s actual generation capacity before approaching the Maharashtra Electricity Regulatory Commission (MERC) for permission to sell the electricity.

Adani Electricity is expected to purchase the power, with the proceeds adjusted against the civic body’s electricity bills. MERC will determine the applicable tariff, which is anticipated to range between Rs 5 and Rs 10 per unit. An earlier proposal to supply electricity to the Bhandup water treatment plant has since been abandoned.

“The actual output could vary depending on the quality and composition of the waste, which will be assessed during the trials,” a BMC official said.

The facility will process fresh waste and cannot accommodate Deonar’s accumulated legacy garbage. Nearly one million tonnes of old waste had to be scientifically relocated and stabilised before construction commenced. Meanwhile, Navayuga Engineering Ltd has been appointed to undertake the bioremediation of 18.5 million tonnes of legacy waste and recover 110 hectares of land.

Operational since 1927, Deonar’s landfill has waste mounds averaging 20 metres in height, with some reaching 40 metres near Rafiq Nagar. Mumbai generates approximately 7,000 tonnes of solid waste daily, of which 500–1,000 tonnes are transported to Deonar, while the remainder goes to Kanjurmarg.

Union Minister of State for Housing and Urban Affairs Tokhan Sahu visited Deonar on Wednesday to review civic projects under the Swachh Bharat Mission-Urban. Officials also briefed him on the waste-to-energy facility and a proposed compressed biogas plant.

Source: Swarajya