Western Railway has successfully completed trials of the indigenous Kavach train-protection system on the 50-km Virar–Mumbai Central suburban corridor. Conducted over two consecutive nights in November 2026, the exercise evaluated the technology’s ability to respond to potentially dangerous railway operating situations.
According to Western Railway Chief Public Relations Officer Arun Kumar Meena, the trials covered six railway lines, including the up and down through lines, fifth and sixth lines, and both Harbour lines. All the prescribed test scenarios were reportedly completed successfully.
The trials assessed several critical situations, including trains approaching red signals, possible rear-end collisions, unexpected halts between stations and instances of overspeeding. Additional checks examined emergency SOS communication, automatic speed regulation, sudden changes in signal indications and safeguards against Signal Passing at Danger (SPAD).
The Kavach system successfully displayed signal information on the locomotive’s Driver Machine Interface across all six lines. Testing also covered permanent speed restrictions and speed regulation on loop lines at Goregaon, Andheri and Borivali, where prescribed limits of 30 kmph and 15 kmph were examined.
Calling-on procedures were evaluated at Andheri Fast and Goregaon Harbour line, while station-based SOS facilities were tested at Borivali and Andheri. Emergency communication during unexpected stoppages was also assessed across the corridor.
Further exercises included SPAD prevention at Vasai Fast and Andheri Harbour, along with testing a sudden change of signal to danger at Kandivli station. A virtual locomotive was used to simulate a rear-end collision, while radio-frequency identification (RFID) tag-reading sequences were checked across the six lines.
Following the exercise, railway personnel resolved minor issues associated with radio-frequency signals and communication systems.
Western Railway said the trials marked progress towards improving suburban railway safety by reducing the possibility of human errors and operational failures.
However, the commissioning schedule for Kavach on this corridor has not been announced. Its effectiveness in regular passenger operations will depend on reliable equipment, adequate communication coverage and consistent implementation of operating procedures.