The Brihanmumbai Municipal Corporation (BMC) is stepping up construction of a new 2,000 million litres per day (MLD) water treatment plant and an equally large pumping station at Bhandup to address Mumbai’s increasing water requirements. Additional Municipal Commissioner (Projects) Abhijit Bangar has instructed officials to speed up construction and complete the infrastructure ahead of schedule.
During a recent inspection, Bangar assessed the progress of civil, electrical, mechanical and water treatment works. He emphasised better coordination between departments, regular monitoring and prompt resolution of construction-related obstacles. He also directed agencies to deploy additional workers and machinery to accelerate execution.
The existing Bhandup Complex, regarded as one of Asia’s largest water treatment facilities, currently has a combined processing capacity of 2,810 MLD. It comprises two plants with capacities of 1,910 MLD and 900 MLD. The proposed facility will add another 2,000 MLD to Mumbai’s treatment capacity.
Excavation for the new treatment plant has reached a depth of 16 metres across approximately six hectares. Bangar has instructed officials to finish the remaining excavation by May 31, 2027, while ensuring the systematic removal and transportation of excavated material.
The upcoming facility will feature several advanced treatment systems, including Actiflo technology, Chlorination Contact Tank, Flow Splitter, Dual Media Filters, Backwash System, Actidyn process and wastewater pumping arrangements. Officials have also been asked to undertake preliminary cement concrete work, electrification and boundary wall construction alongside excavation to prevent delays.
Progress on the matching-capacity pumping station is also advancing. Against the proposed excavation depth of 20.5 metres, nearly 18 metres have been completed. Excavation for the bypass line, rising main and pump house building has been fully finished.
Meanwhile, work on the inlet chamber and clear water pumping sump has reached approximately 85% completion. Concreting of all 179 micropiles has also been completed.
Bangar has further directed officials to establish specific construction deadlines and carry out electrical and civil works simultaneously to ensure timely completion of both projects.
Source: The Free Press Journal