Ashwini Vaishnaw Says Mumbai-Ahmedabad Bullet Train Services To Begin By Late 2027

India’s first high-speed rail project connecting Mumbai and Ahmedabad is progressing rapidly, with the first passenger service targeted for the final quarter of 2027, Union Railway Minister Ashwini Vaishnaw announced on Friday. The 508-km corridor has moved beyond the planning phase, with major construction activities advancing across Gujarat and Maharashtra.

Highlighting the project’s progress, Vaishnaw said, “India’s first bullet train is no longer an announcement. It is 508 km of construction, moving at full pace. The first service begins in the last quarter of 2027!”

Once operational, the high-speed service is expected to reduce travel time between Mumbai and Ahmedabad to less than two hours, compared with approximately eight to nine hours by road.

The minister said the corridor would strengthen economic connections between several important cities, including Mumbai, Thane, Vapi, Surat, Vadodara, Anand and Ahmedabad, supporting faster movement of passengers, businesses and commercial opportunities.

The foundation stone for the project was laid in September 2017 by Prime Minister Narendra Modi and the Japanese government. Japan is providing high-speed rail technology that has operated for more than 60 years without a passenger fatality. However, land acquisition challenges in Maharashtra and the Covid-19 pandemic affected the initial construction schedule. Large-scale work gained momentum from 2021 onwards.

Designed for a maximum speed of 350 kmph, the trains are expected to operate at 320 kmph. Approximately 465 km of the corridor is being developed on elevated viaducts to eliminate level crossings and improve operational safety.

According to the minister, by September 2026, pier construction had been completed across 456 km, while viaduct work covered 371 km. More than six lakh noise barriers had been installed along 299 km, alongside 9,300 overhead equipment masts across 206 km.

Excavation of four mountain tunnels has been completed, while work continues on the 21-km tunnel in Maharashtra, including approximately 5 km excavated through mountain tunnelling methods. The project also features India’s first undersea rail tunnel beneath Thane Creek.

Civil construction at eight stations has been completed, with finishing work underway. Depots at Sabarmati, Surat and Thane are also progressing.